belmazad.comTender programme · issued 1 October 2026 · Revision 6 · prepared by Belmazad with GAT

Programme of works

Roshdy Building — Tender Programme

Misr Abu Dhabi for Real Estate Investments · Belmazad with GAT

weeks
Roshdy  Sphinx
————
1 October 2026 · Revision 6
Belmazad GAT Belmazad + GAT (joint) MAD (client) Bidders ◆ Milestone Red underline = critical path (zero float to completion)
Zoom

Company is the responsible party; Discipline the team; Belmazad + GAT is joint work (split bar). Milestones are diamonds; the last row of each project is held float. Hover a bar for its dates. Use the tabs to view each project or both together; the Sphinx launch after Roshdy launch box in the header lets you try other launch gaps (not saved). Red underline = critical path. Zoom with − / Fit / +, and export to Excel or PDF.

All durations are working days on a Sunday–Thursday week; calendar dates are shown. Egyptian public holidays are excluded (Islamic dates ±1–2 days for moon sighting; a holiday falling on a weekend is taken on the next working day); the four Thursdays of Ramadan 2027 are treated as non-working to reflect reduced working hours. Roshdy’s submission deadline is set before the late-December holiday period. MAD approvals are 4 working days; the complete tender package 8 (Sphinx 12, Board-level); one shortlist decision covers financial opening and negotiation, and MAD’s acceptance of the evaluation report confirms the negotiation mandate proposed in it; a longer approval moves everything after it. Responsibilities follow the Belmazad–GAT–MAD responsibility matrix: GAT reviews available information and bidder-supplied investigations and does not undertake fieldwork; investigations MAD decides to procure are shown as client tasks feeding the data room. Each project's contractual period runs from its anchor milestone — Roshdy from Commencement (programme approved and documents received), Sphinx from MAD's launch instruction, with preparation done in parallel beforehand and postponement of up to two months permitted. Two negotiation rounds are planned per project (a round covers all shortlisted bidders and their revisions); one additional round where reasonably required extends the programme by up to two weeks without penalty. Evaluation durations assume 6–10 Roshdy bids and 4–8 Sphinx bids and are subject to GAT's confirmation of its named team and review methodology. Float is held before each completion milestone. Standing activities (progress reporting, GAT's parallel manual delivery) are drawn as thin bars and do not drive the dates. Stage 7 (MAD's award decision, final questions, closeout) is MAD's period and sits outside the consultant's commitment.